Book a shared unloading bay and crane for two site deliveries
Build a delivery slot from arrival to release of the bay. A worked Belgian site schedule shows how to move the second truck after a delay.
When two suppliers need the same unloading bay and crane, book the whole occupation time for each delivery. The first truck’s arrival time tells the second supplier very little unless someone can also say when the bay will be clear. Use the site’s working language for the confirmation and repeat the times, job reference and entrance in writing.
Find the constraint before confirming the booking
Consider a Brussels refurbishment where one vehicle at a time can enter the courtyard. The site lead checks the truck type, packaging, receiving area and handling equipment for each load. The competent people on site remain responsible for assessing access, lifting arrangements and safe execution. A booking sheet coordinates use of the space. It cannot authorise a lift or promise the street outside is available for waiting.
Ask whether the supplier is offering an exact appointment or an estimated route window. If the answer is a three-hour window, agree when the driver will call and who can approve a revised slot. On a multilingual site, give the driver the entrance street and the purchase order number. The postal address alone may take them to the customer’s front door.
Put release time on the programme
Suppose a load of frames is due at 08:15. The estimated time is ten minutes for arrival and setup, thirty-five minutes for unloading and ten minutes to clear the vehicle and release the bay. The first slot therefore ends at 09:10. Allow a ten-minute operating buffer before the second delivery. The next supplier can be offered 09:20, subject to confirmation.
The second truck carries insulation and needs another forty minutes. Receiving staff should plan for the bay to be occupied until 10:00. The installation crew may need a later start if packs must still be moved to the upper floor. Record that separately so the crew is not sent to an empty work area simply because a delivery was signed for at the gate.
Change the booking when a truck is late
At 08:00 the first driver says they will arrive at 08:40, twenty-five minutes late. If the unloading operation is unchanged, the bay becomes free at 09:35. Keeping the ten-minute buffer means offering 09:45 to the second supplier. Contact that supplier and the receiving team. Do not assume an edit on the internal planning board has reached the dispatcher.
If the second driver cannot change their route, ask the site lead about another feasible slot or an approved alternative receiving point. A crew might be able to start another task while waiting, but only if the required area and tools are available. Record who accepted the new sequence and which dependent task is still at risk.
Keep an actual time alongside the estimate
A compact delivery record contains job, supplier, order reference, contact, unloading resource, booked start and planned release. After the delivery, add the actual start and release time and explain any material difference. If setup repeatedly takes longer for one type of load, improve that estimate rather than adding the same allowance to every supplier.
The crane and the bay need not be released at the same minute. If the last pack lands at 09:00 but the truck occupies the entrance until 09:10, another approved internal lifting task may be feasible before the next truck can enter. Show both release times when the distinction affects a decision. Otherwise someone looking only at the crane booking may send the next truck into an entrance that is still occupied.
The Belgian construction research centre Buildwise describes coordinating deliveries with crane occupancy in its site logistics guidance, in French. Read the construction capacity planning guide alongside the delivery record. For a discussion with Enfin, bring one busy morning’s orders and ask how the site and office would each see the revised appointment.
How much crew time can you book when only two rooms are ready?
Confirm crew time for partially released rooms by reconciling labour-hours, access times, waiting and the actual visit schedule.
Several construction deliveries on one Peppol invoice: retain the tax-point date per line
Keep delivery or service dates traceable when several site transactions share one structured invoice and one payment request.
A Peppol summary invoice for several construction deliveries: preserve each delivery date
Combine several deliveries only when the invoice remains traceable to approved site records, tax dates, quantities and purchase references.