How to split one haulage invoice between two Belgian jobs
Allocate one haulage invoice across two Belgian jobs using the agreed stops, weight, surcharges and subsequent credit.
Two site receipts reference one €360 carrier invoice, excluding VAT. Site A took three tonnes and site B one. A weight-only allocation gives €270 and €90. If the agreed tariff includes €40 for each drop, allocate the remaining €280 by weight. The project costs become €250 and €110. Adding both original shares and two drop charges would overstate cost by €80.
Keep the carrier reference, signed weights and both purchase-order numbers together. A site manager should be able to reproduce either share without opening the other project's budget.
Construction purchase orders from approval to delivery
Read the rate card before choosing a split
A carrier may quote one price for the vehicle, a charge for each stop, or a rate per tonne. Ask the buyer which quotation applies to this trip. A reasonable internal split is easier to defend if the order describes it before the invoice comes in. Where the rate card specifies a drop charge, assign each drop to the job that received it. Then split the shared part of the journey.
The purchase value can be misleading. Say site A’s three tonnes cost €900 and site B’s one tonne cost €2,100. A split by goods value gives A €108 of the haulage cost and B €252. It charges the lighter, more valuable load most of the journey. That calculation might suit value-based insurance. It poorly represents a carrier billing for weight and stops.
Work from what came off the truck
Gather the two delivery notes. Write the carrier’s trip number on each, with the receiving site and its purchase-order reference. Check the received weight. If the supplier ordered four tonnes but the receiving crew sent part of a pallet back, separate the delivery discrepancy from the transport allocation. A purchase order alone cannot establish the weight received at each site.
Record the first allocation as €40 + €280 × 3/4. Record the second as €40 + €280 × 1/4. Add the €250 and €110 project entries and compare the sum with the carrier’s net invoice line. If the buyer already included an estimate for haulage on either order, identify which provisional entry the invoice replaces.
When one site causes a second trip
Assume the carrier charges an additional €60 to revisit site B. If the carrier identifies that visit separately, the complete invoice is €420 and the project shares become €250 and €170. Redistributing all €420 by weight would pass some of B’s extra visit to A. If the surcharge came from a diversion affecting the entire journey, keep the reason with the allocation and reconsider the common share.
A missing delivery note is a good reason to keep an allocation provisional. Name the person who will obtain the weight, record the assumption used at month end and correct both jobs together. Otherwise the correction moves only one margin while the other job keeps its provisional cost.
Use the same evidence if a credit arrives later. A credit for the whole trip can follow the common split. A credit specifically for a failed drop belongs with the cost of that drop. Someone reviewing a job months later should be able to reconstruct its share from the tariff, receipt and linked project entries.
Returns and credits need their own allocation check
A rejected pallet may still have travelled the full route. Received weight is evidence to reconcile, not a universal billing rule. Check whether the agreed carrier basis is loaded weight, delivered weight, vehicle time or a fixed charge. The three-to-one split in this fictional example assumes that basis has been confirmed. Keep any return journey separate. A supplier credit for rejected goods does not automatically reduce the carrier’s charge.
Now assume the carrier credits €28 against the shared journey only. Both €40 drops remain payable, so the shared cost falls from €280 to €252. Site A becomes €40 + 3/4 × €252 = €229. Site B becomes €40 + 1/4 × €252 = €103. The revised total is €332. Reductions of €21 and €7 reconcile exactly to the €28 credit. A credit specifically for one drop would follow that drop instead.
Keep the original invoice reference, credit reference, previous allocation, corrected allocation and reviewer together. Have someone reconstruct the calculation without relying on the person who first entered it. Every example amount is before VAT; this project-cost exercise does not establish the tax treatment or recoverability of a real invoice. When assessing software, ask to enter the correction and reopen both projects. An attachment alone does not prove that automatic cost splitting exists.
Keep the allocation beside the credit
- Original allocation — Site A: €250; Site B: €110; Total: €360.
- Shared-journey credit — Site A: −€21; Site B: −€7; Total: −€28.
- Corrected allocation — Site A: €229; Site B: €103; Total: €332.
This allocation concerns the original journey, without the separate €60 redelivery example. Add the journey reference and credit reference. A correct total alone does not identify which trip was corrected.
Bring this allocation sheet to an Enfin demonstration. Ask to reopen the invoice and both projects, and identify which allocations require manual entry.
Move surplus materials between jobs without charging the purchase twice
Follow a batch from dispatch to acceptance. Reconcile the physical quantity, usable stock and job cost when the receiving crew finds a discrepancy.
Software for Belgian plumbing contractors: schedule jobs and invoice faster
Software for Belgian plumbing contractors: schedule jobs and invoice faster. Compare workflows, data and implementation across Belgian construction.
Move from Excel to construction software without disrupting live jobs
Move from Excel to construction software without disrupting live jobs. Compare workflows, data and implementation across Belgian construction.