Forecast final job margin with open purchase orders
Use a Belgian contractor’s worked example to reconcile posted costs, outstanding orders and the cost of remaining work before handover.
A job report can show a healthy balance on Friday even though the contractor still has to pay for the last delivery and send a crew back for commissioning. To forecast the final margin, compare approved sales with the cost you expect to have incurred by completion. Use one cut-off date for purchases, labour and changes in scope.
Forecast margin M34: what should change when the installer invoices?
A Belgian contractor has agreed a €12,000 joinery package before VAT. The fictional job already carries €7,500 of actual costs. An outstanding subcontract installation order covers another €2,500. A separate final clean still has €500 of budgeted work remaining. The cleaning allowance is outside the installation order.

Before the installation invoice, actual costs are €7,500 and commitments are €2,500. Forecast final cost is €10,500.
Subtracting only booked costs from revenue leaves €4,500. The job still has to absorb the order and the cleaning allowance. Forecast margin is therefore €1,500, or 12.5% of revenue: €12,000 less €7,500, €2,500 and €500.

After matching, actual costs rise to €10,000, the open order falls to zero and forecast margin stays at €1,500.
The office matches the subcontract invoice to the existing order. Its €2,500 changes category from committed to actual. If both columns still include it, check the invoice link and the quantity it covers before treating the apparent loss as a cost overrun. The final clean remains a separate estimate.
Make each euro appear in one place
Start with costs already charged to the job. Include recorded labour at the company’s chosen internal cost and the materials or subcontract work already recognised in its job reports. Next, list outstanding purchase commitments. Only the part that has not already reached the job cost report belongs here. Finally, estimate the cost of work still required that neither of those columns covers.
On the sales side, use the accepted quotation and agreed variations, excluding VAT. If a variation is awaiting approval, show it separately with the amount and the person following it up. If the crew has already spent time on that work, include the cost. Leaving it out alongside the unsigned sales value would conceal how much is at stake.
Work through a fit-out in Brussels
Consider an English-speaking contractor fitting out a small office. The agreed sales value is €68,000. Materials, subcontract invoices and labour already charged come to €36,800. A joinery order totals €11,400. The supplier has invoiced €6,900 of it, which is already in the €36,800. The outstanding order contributes €4,500 to the forecast.
The site lead expects another 105 hours of fitting and commissioning at an internal cost of €44 per hour. An unplaced order for trims and fixings will cost a further €1,580. That gives €6,200 of remaining costs outside the order book. Forecast cost is therefore €36,800 + €4,500 + €6,200, or €47,500. The expected direct job margin is €20,500, approximately 30.1% of approved sales. If the business allocates office overhead to jobs, show that allocation separately and compare figures prepared on the same basis.
Follow one invoice through the next review
Suppose the joinery company submits a matching €2,000 invoice. Posted costs rise to €38,800 and the unrecognised commitment falls to €2,500. The forecast still totals €47,500. A forecast that rises by €2,000 signals a reconciliation problem unless something else changed. Check the order line, delivered quantity and job reference before asking the project manager to explain a supposed overrun.
Now suppose access to the plant room changes and commissioning will take twelve extra hours. At €44 per hour, the genuine movement is €528. With no approved change in sales, margin drops to €19,972. The site lead can price the disruption, discuss access or revise the sequence. Keep the possible sales adjustment visible as a separate decision until the client has agreed it.
Give the next reviewer a starting point
Keep the dated forecast, the supplier references and an owner for each uncertain quantity. Ask someone who has seen the work to check the remaining hours. An invoice that covers half the contract price does not establish that half the labour is complete. If there are two feasible completion methods, show the cost of each and identify the decision date.
Pay particular attention to delivered but uninvoiced materials. Some job reports recognise a goods receipt before accounts payable posts the invoice. Others show only the posted invoice. Trace one actual order line into the report you are using. If the receipt is already in posted job costs, remove that value from the outstanding commitment. If the delivery is only a physical record, leave its financial value in the open order column for now.
At handover, compare the last estimate with final costs and record the assumption that made the largest difference. This creates a reference for the next estimate without rewriting what the team knew at the time. Buildwise describes the contractor’s responsibility for forecasting remaining work in its Belgian site management guide, in French. For a software review, use the construction job costing guide and bring a partly invoiced order to a demo with Enfin.
Construction purchase orders from approval to delivery
Construction purchase orders from approval to delivery. Compare workflows, data and implementation across Belgian construction.
Migrating open quotes and deposits: reconcile each construction job
Check quote versions, existing invoices, payments and unfinished billing when moving live construction jobs into new software.