Turn one bill-of-quantities item into several site tasks

Keep the sale quantity, work quantities and completed measurement separate. A Belgian partitioning example connects the estimate to the weekly programme.

Enfin editorial team4 minute read

A bill of quantities groups work for pricing and measurement. A programme groups activities so people can actually do the work. When one priced item needs three trades or passes, link all three tasks to the same item reference and keep one authoritative sale quantity. This matters on Belgian jobs where the site team may work from a French métré or Dutch meetstaat while the project manager reports in English.

Start with the finished item

Consider 100 square metres of completed partition at an illustrative €88 per square metre. The priced item totals €8,800 and includes framing, boarding and finishing. Assigning each operation a planning task does not create three separate entitlements to charge €8,800. Each task describes work the team must perform to deliver the one item.

Record the item reference, area or room, task name, work quantity, expected crew hours and the condition that releases the work. Keep the measurement convention with the priced item. For example, the area used to order sheets, including cuts and both faces where applicable, may differ from the measured area of a finished partition. Write the unit beside every quantity.

Split tasks where access actually changes

The floor has an east wing with 60 square metres and a west wing with 40. Framing is complete in both. Services in the east wing have been checked and that area has been released for closing. In the west wing a connection still needs inspection. The boarders can start in the east. Give the west-wing release an owner and a time to review it.

Later, framing can correctly be reported as 100 square metres complete even though only 60 square metres of partition are fully finished. For a report that specifically measures finished partitions, the answer is 60. Adding 100 to 60 would mix a work activity with the finished item. If intermediate stages are payable, refer to the agreed valuation rule and evidence. Never infer the amount due merely from the number of task boxes ticked.

Work out labour separately

Suppose the estimate allows 0.25 labour hours per square metre for framing, 0.50 for boarding and 0.15 for finishing. For the whole floor that gives 25, 50 and 15 hours respectively, or 90 labour hours. A two-person crew working simultaneously can deliver ten labour hours in five elapsed hours under suitable conditions. Waiting for access, drying or a preceding trade can still lengthen the programme.

When the crew discovers a different installation method is needed, revise the time allowance with a reason. Keep the original allowance available for comparison. An added ten square metres requested by the client is a different event. Link that change to its approval and then adjust quantities and labour for the affected zones.

Try the handover in both directions

Give a supervisor one task and ask them to locate the priced item, current drawing and release condition. Then give the estimator one priced item and ask them to list its site tasks and explain how completed quantity will be measured. If a setup activity serves two items, split the hours using a documented basis or keep them under a separate internal activity. Charging all the setup hours to both items will overstate the plan.

A spreadsheet export can quietly reintroduce the error. If it repeats the sale value on every activity row, a simple column total will report three times the order value. Keep a priced-item table and a task table joined by the item reference. Check that the east and west zone areas sum to 100 square metres in the measurement record. Sum the labour hours in the task table, where adding all three operations is appropriate.

Buildwise explains the structural difference between bills of quantities and schedules in its Coplaco overview, in Dutch. The bill of quantities software guide covers the estimating side. Bring one composite item and its weekly site plan to a discussion with Enfin to test the handover against the way your own team works.